Repaving Project to Impact Traffic on West Lincoln Avenue

A grind and overlay project on West Lincoln Avenue in the Gilbert Park area will begin on Monday, August 4th

The project will require closure of the eastbound lane of West Lincoln at 52nd avenue between 6:00 am and 4:00 pm on weekdays. Eastbound traffic will be detoured North on 52nd Avenue around the construction activity. While local access will be maintained during the road work, traffic delays in the area are likely to occur. Drivers should use alternate routes if possible until the project is completed.

The repaving work on West Lincoln will go from 42nd Avenue to 52nd Avenue and should be completed by August 21st.

As always, the schedule for this type of a project is subject to change daily dependent on weather, equipment failure, and emergencies.

For additional information about this project, contact Streets and Traffic Operations Manager Joe Rosenlund at 576-6430.

 

Lincoln Avenue Repaving News Release – 8-01-14