Forty-Eighth Avenue will be closed between Summitview Avenue and Chestnut Avenue from Monday, June 2nd, through June 5th for a road replacement project.
Crews will tear out and replace this section of roadway starting at 6:30 am Monday. It is hoped work will be completed in time to re-open 48th Avenue by noon on Thursday, June 5th.
A detour route will be posted on 56th Avenue and 40th Avenue.
Access to properties in the project area will be maintained while work is ongoing.
As always, the schedule for this type of a project is subject to change daily dependent on weather, equipment failure, and emergencies.
For more about this project, contact Street Maintenance Supervisor Jay Kendall at 509-576-6443.