This Wednesday, June 5th, City of Yakima crews will begin a series of traffic signal head upgrades at intersections over the next several weeks. The intersections listed below will be reduced to a single lane of traffic in each direction, with stop signs posted in all directions.
Traffic impacts for the signal upgrades are scheduled to begin at 6:30 am and by complete by 12:00 pm. Signals at the intersections will be dark during project work hours
- June 5th 1st Ave & Lincoln Ave
- June 26th 3rd Ave & Lincoln Ave
- July 10th 5th Ave & Lincoln Ave
- July 17th 5th Ave & Martin Luther King Jr. Blvd
- July 24th 3rd Ave & Martin Luther King Jr. Blvd
- July 31st 1st Ave & Martin Luther King Jr. Blvd
- August 7th 16th Ave & Yakima Ave
- August 14th 16th Ave & Summitview Ave
- August 21st 16th Ave & Fruitvale Blvd
Drivers are reminded the speed limit through all traffic-related work zones within the City of Yakima is 20 miles-per-hour.
As always, the schedule for this type of project is subject to change daily dependent on weather, equipment failure, and emergencies.
For more information, contact Traffic Operations Supervisor Dan Nickoloff at 509-576-6746.