The City of Yakima has begun a series of traffic signal head upgrades at intersections over the next several weeks. The intersections listed below will be reduced to a single lane of traffic in each direction, with stop signs posted in all directions.
- July 9th 3rd Ave & Mead (complete)
- July 16th 3rd Ave & Walnut
- July 23rd 5th Ave & Walnut
- July 30th 5th Ave & Yakima
- Aug. 6th 8th St & Yakima
- Aug. 13th 16th Ave & Cherry
- Aug. 20th 44th Ave & Tieton
- Aug. 27th 1st St & Arlington
- Aug. 28th 1st St & Arlington
Traffic impacts for the signal upgrades are scheduled to begin at 6:30 am and by complete by 12:00 pm. Signals at the intersections will be dark during project work hours. Drivers should treat the intersections as four-way stops while work is in progress.
Drivers are encouraged to slow down in all traffic-related work zones.
As always, the schedule for this type of project is subject to change daily dependent on weather, equipment failure, and emergencies.
For more information, contact Traffic Operations Supervisor Dan Nickoloff at 509-576-6746.